Skip to main content

Time Flow Benefits

Why the Time Flow helps keep your work flow in order

Aaron Wittman avatar
Written by Aaron Wittman
Updated yesterday

Introduction

The Time Flow board is a kanban-style project management tool designed to give you a realistic, calendar-based view of your work. Unlike traditional kanban boards that simply track status, Time Flow treats your tasks like appointments in your calendar—helping you understand not just what needs to be done, but when you're actually going to do it.

Understanding "Not Started" Work

The Past is Past

One of Time Flow's most powerful features is how it handles work that hasn't been started yet. The board clearly shows you all tasks with a "to-do" status where the start date has already passed.

This is your reality check.

Here's the key insight: you cannot go back in time to start work. Unless you own a time machine, that task with a start date of last Tuesday cannot be started last Tuesday—it needs to be rescheduled to when you'll actually begin it.

Moving Work Forward

When you see work in the "Not Started" section, you need to move it to either:

  • Today - if you're going to start it right now

  • A future date - when you realistically plan to begin

Think of this exactly like rescheduling a calendar meeting. You wouldn't leave a missed meeting on last week's calendar—you'd move it to a new time slot. The same principle applies to your tasks.

The "Today and Future Dates" View: Your Work Diary

The "Today and Future Date" columns function as your diary of scheduled work. This section shows:

  • Today - Work scheduled to start today

  • Future dates - Your calendar of upcoming work and when it needs to start

This creates a clear pipeline of what you need to focus on and when. As soon as you start working on a task, it automatically moves from "the date in the future" to "In Progress, and start date of today", giving you an accurate snapshot of your current workload. As you take on future work, this helps update your capacity.

The Power of Four Critical Views

Time Flow gives you four essential columns that work together to create complete visibility:

  1. Not Started (Overdue Starts) - What got missed and needs rescheduling

  2. Future Work - Your calendar of today and future work starts

  3. In Progress - What's being worked on right now

  4. Overdue - Work that has passed its due date and needs immediate attention

Why Each Column Matters

Not Started shows you the planning failures—tasks that were supposed to begin but never did. This is your prompt to be realistic and reschedule.

Future Work is your commitment calendar—what you've promised to start today and in the future. This keeps your pipeline visible and manageable.

In Progress reveals your current workload—everything actively being worked on. This prevents the common problem of having too many things "in flight" at once.

Overdue is your accountability column—work that has blown past its deadline. This creates urgency and ensures nothing gets forgotten just because it's late.

The Complete Picture

Together, these four views create powerful transparency:

  • You can immediately see what fell through the cracks (Not Started)

  • You know what's on your schedule (Coming Up)

  • You understand your current active workload (In Progress)

  • You're confronted with what's late and needs urgent attention (Overdue)

This combination means you always know the full story: what got missed, what's planned, what's happening now, and what's already late. No task can hide, and no excuse can mask reality.

True Capacity: The Three Essential Elements

For Time Flow's capacity features to work effectively, every task must have three pieces of information:

  1. Start date - When work begins

  2. Due date - When work must be completed

  3. Estimated hours - How long the work will take

Why All Three Matter

Let's look at why you need all three elements with a practical example:

Example 1: The Incomplete Picture

  • Task: "Write quarterly report"

  • Due date: Friday

  • Estimated hours: 8 hours

Without a start date, you don't know if this is starting Monday (giving you the whole week) or Thursday (leaving you just one day). The capacity calculation can't accurately distribute the workload across your week.

Example 2: The Complete Picture

  • Task: "Write quarterly report"

  • Start date: Monday

  • Due date: Friday

  • Estimated hours: 8 hours

Now the system knows you have 8 hours of work spread across 5 days. If you work 8-hour days, that's approximately 1.6 hours per day—a manageable load that can be balanced against other tasks.

Example 3: Understanding Daily Load Imagine you have three tasks all starting Monday:

  • Task A: 12 hours over 3 days = 4 hours/day

  • Task B: 8 hours over 4 days = 2 hours/day

  • Task C: 6 hours over 2 days = 3 hours/day

Your capacity view shows you need 9 hours of work on Monday—immediately revealing you're over capacity for a standard 8-hour day. This allows you to make informed decisions about rescheduling before you're buried in overdue work.

Capacity is Always "Today's Value"

Here's a critical concept: capacity is calculated based on today's reality.

Overdue Work

All overdue work is treated as needing to be completed today. If a task was due yesterday with 4 hours remaining, those 4 hours are added to today's capacity requirement. This creates urgency and prevents overdue work from disappearing into the background. (You can turn this off in the board settings).

In Progress Work

Work currently in progress contributes to today's capacity based on remaining hours and the current due date. If you're halfway through an 8-hour task due tomorrow, you have approximately 4 hours of capacity allocated today and 4 tomorrow.

The Future is Fluid

You can look ahead to see what a future day might look like if everything stays the same—but understand this is a snapshot, not a guarantee. Here's why:

  • New tasks will be added

  • Priorities will shift

  • Work will take longer (or shorter) than estimated

  • Start and due dates will be adjusted

Think of future capacity as a weather forecast—useful for planning, but expect things to change as you get closer to the actual date.

Today is What Matters

Your most accurate capacity view is always today. This is where planning meets reality. Your today view shows:

  • Overdue tasks that must be addressed now

  • In-progress work that needs continued attention

  • New work scheduled to start today

  • The total hours required versus hours available

This daily focus keeps you grounded in what's actually achievable right now, rather than getting lost in theoretical future planning.

How It All Works Together

Let's walk through a realistic scenario:

Monday Morning:

  • You have 3 tasks "Not Started" from last week (overdue starts)

  • You have 2 tasks scheduled to start today in "Coming Up"

  • You have 4 tasks "In Progress" from Friday

  • You have 2 tasks in "Overdue" that passed their due date

Your workflow:

  1. Review the "Not Started" section—reschedule those 3 tasks to realistic start dates

  2. Check the "Overdue" column—these tasks add to today's capacity and need immediate attention

  3. Check your capacity for today—do you have room for the 2 new starts plus continuing the 4 in-progress tasks plus the 2 overdue items?

  4. If over capacity, move some "Coming Up" work to future dates or negotiate new deadlines for overdue work

  5. Start working—as you begin tasks, they move from "Coming Up" to "In Progress"

  6. Complete tasks and watch your capacity free up

Tuesday Morning: Yesterday's incomplete work is now contributing to today's capacity. Any tasks that missed their due date yesterday have moved to "Overdue." Your "Coming Up" column shows what's scheduled to start. You make adjustments based on Monday's reality and plan Tuesday accordingly.

The Benefits of Time-Based Workflow

This approach creates several powerful advantages:

Honesty about workload - You can't hide overdue or missed work; it's visible and demands attention

Realistic planning - By forcing start date decisions, you commit to when work will actually happen

Capacity awareness - You see the hours required each day, preventing overcommitment

Clear priorities - Today's work is always front and center, with future work properly queued

Accountability - The board shows what got missed, what's in progress, what's coming, and what's overdue—creating transparency for teams

Conclusion

The Time Flow board succeeds because it aligns your project management with how time actually works. You can't start work in the past, capacity is always about today's reality, and effective planning requires knowing when work starts, when it's due, and how long it takes.

By treating your tasks like calendar appointments and requiring complete capacity information, Time Flow transforms your board from a simple status tracker into a powerful time management and capacity planning tool. You'll always know what needs your attention now, what's coming next, whether you have the capacity to take it on, and what's overdue and demanding immediate action.

Did this answer your question?